Case Study - Summertown Pavilion

Project overview

Extensive refurbishment of internal office accomodation including strip out of former tenants installations,new glazed partitions, new comfort cooling, new LED lighting upgrade, new oak plank flooring, new ceilings and bespoke formed bulkheads, new kitchen, and male,female,and multi-use WC facilities.


Value: £221,000.00

Duration: 12 weeks

Completion: November 2022